Run a Model Launch Readiness Review

4 min readadvanced1–2 weekendsForAI TPMAI Infrastructure PM

Build with your agent

Copy the prompt, keep the brief as the source of truth

Paste it into Claude Code, Cursor, Codex or ChatGPT. It points your agent at this page and sets the working rules; the brief, steps and acceptance criteria stay in one place.

Read https://www.productinterview.tools/projects/launch-readiness-review/ and build it.
Follow the scope and acceptance criteria exactly.
Ask me up to five questions before starting.
Use synthetic or public data only.
Keep PLAN.md, DECISIONS.md and EVALS.md.
Do not add dependencies without asking.
Stop after each milestone and show me the evidence.
Finish with the deliverables and presentation described in the brief, including a one-page write-up and a 60-second demo script.
On this page
  1. What you'll build and why it impresses
  2. The brief
  3. Steps
  4. Acceptance criteria
  5. How to present it
  6. What interviewers will probe
  7. Variations

What you'll build and why it impresses

A launch readiness review is where a TPMTechnical Program Manager. Owns plans, dependencies, risks and delivery for large cross-team programmes. Read the full explanation earns their salary. It is also easy to describe and hard to do well: anyone can list workstreams; the skill is knowing which dependency will slip, which risk has no owner, and what evidence the go/no-go decision actually needs.

This project asks you to run a full readiness review for a hypothetical model launch. You will produce the programme plan, the critical path, the risk log, the decision gates, the rollback plan and the communications plan — then present it as if the launch is in two weeks.

What it proves: you can structure a complex launch, surface the uncomfortable risks, and make a recommendation when not everything is green. That is the core of AI programme management.

The brief

Launch. A model update for one product surface. Good choices: a coding assistant moving to a new model version; a support agent adding a tool; a summariser launching to a new region. Pick one with real dependencies across research, infrastructure, safety and product.

Scale. Assume a staged rollout: internal, then 5% of users, then 25%, then 100%. The product has meaningful usage, so a regression will be noticed.

Teams. Name the workstreams and owners: research, model evaluation, safety, infrastructure and serving, product and design, support, legal and communications. You can invent names, but give every workstream an owner.

Constraints. A fixed launch date, but not a fixed scope. One workstream will slip. The review must show the trade-off.

Out of scope. The full product spec and the model training plan. Stay on launch readiness.

Steps

  1. Write the launch definition. What changes for users, what does not, and what "ready" means. Include the success metrics and the guardrail metrics. A launch without a definition of done cannot be reviewed.

  2. Build the workstream plan. For each workstream: deliverables, owner, dependencies and the evidence they must produce for the review. Keep it to one page.

  3. Map the critical path. Identify the longest chain of dependent work. Mark the items with zero float. Then introduce a realistic slip: a safety evaluation needs another week, or a serving capacity order arrives late. Show the impact.

  4. Build the risk log. For each risk: likelihood, impact, owner, trigger, mitigation and contingency. Include the risks people avoid writing down: an eval that may not be trustworthy, a support team that is not trained, a rollback that has never been tested.

  5. Define the decision gates. Before each rollout stage: what evidence is required, who signs off, and what happens if the evidence is missing. Separate "must pass" from "monitor". Use the eval plan framework for the quality gates.

  6. Write the go/no-go checklist. A one-page list a room can walk through: quality, safety, capacity, support, legal, communications and rollback. Each line has an owner and a status.

  7. Write the rollback and incident plan. How to revert, who decides, how long it takes, what users see, and how you communicate. Test the rollback path on paper at minimum.

  8. Present the review. Give a recommendation: go, go with constraints, or no-go. State the residual risk, the open items and the decision you need from the room. Include the dissenting view.

Acceptance criteria

  • A one-page launch definition with success and guardrail metrics.
  • A workstream plan with owners, deliverables and evidence.
  • A critical path with float and a realistic slip scenario.
  • A risk log with owners, triggers, mitigations and contingencies.
  • Decision gates for each rollout stage, with must-pass criteria.
  • A go/no-go checklist with status and owners.
  • A rollback and incident plan.
  • A written recommendation with residual risk and open decisions.
  • A communications plan covering internal, customer and public messaging.

How to present it

In the review: start with the recommendation and the biggest risk. Then the plan, the critical path and the gates. Do not walk through every workstream; walk through the decisions.

In the TPM interview: the interviewer will challenge one dependency and one risk. Show how you re-plan and what you would cut. The quality of the trade-off matters more than the completeness of the plan.

In a portfolio: publish the redacted plan and a short note on what changed after the review. The ability to update the plan is part of the skill.

What interviewers will probe

  • What is on the critical path? Name the chain and the float. If everything is critical, nothing is. See a dependency is slipping.
  • Which risk would you escalate first? The one with high impact, no owner and a late trigger. Explain why.
  • What evidence do you need to go? Quality, safety, capacity and support, with must-pass thresholds set in advance. See the launch go/no-go meeting.
  • What if safety finds a regression the day before launch? Delay or constrain the rollout. Have the decision rule ready. See a safety regression before launch.
  • How do you roll back? A tested path, a named decision-maker and a customer communication. "We will figure it out" is not a plan.
  • How do you communicate a delay? Early, with the reason, the new date and what is needed. Do not surprise stakeholders.

Variations

Easier: one product surface, four workstreams, no slip scenario. Still write the risk log and gates.

Harder: add a second launch that shares a dependency; model a capacity shortage; add a regulatory or enterprise customer constraint; or run the review with a colleague playing a skeptical executive.

Team version: one person owns the plan and critical path, one owns risks and gates, one plays safety and support. Present the disagreement about readiness as the finding.