Plan the Programme for a Large Training Run

The interviewer asksYou're the TPM for a training run starting in three months. Plan the programme.

AI TPMModel PM (secondary)AdvancedExecution roundRepresentative10 min

On this page
  1. The 30-second version
  2. What it's really testing
  3. How to structure your answer
  4. The interview, played out
  5. The strong answer, distilled
  6. How it's scored
  7. How the answer changes by role
  8. Common mistakes
  9. More follow-ups to practise
  10. Go deeper
  11. Sources

The 30-second version

  1. Workstreams: data, compute, training infrastructure, evals, safety.
  2. Critical path: usually data readiness and cluster reliability.
  3. Milestones: data freeze, cluster burn-in, small-scale test run, start, checkpoints with evals.
  4. Decision points: go/no-go at start and at checkpoints, with criteria agreed in advance.
  5. Risks: hardware failures, data issues, eval readiness; owners and contingencies.

Watch it played outSee the strong answerHow it's scored

What it's really testing

  • Programme planning
  • Critical path
  • Risk management

How to structure your answer

  1. Workstreams.
  2. Critical path.
  3. Milestones.
  4. Decisions.
  5. Risks.

The interview, played out

A written example interview, not a real candidate or company transcript.Strong move
  1. Interviewer
    You're the TPMTechnical Program Manager. Owns plans, dependencies, risks and delivery for large cross-team programmes. Read the full explanation for a training run starting in three months. Plan the programme.
  2. Candidate
    Five workstreams, each with an owner: data, compute, training infrastructure, evals, and safety. I'd map dependencies between them.
  3. Candidate
    The critical path is usually data readiness and cluster reliability. So milestones: data freeze six weeks before start; cluster burn-in to find bad hardware; a small-scale test run two weeks before; then start.
  4. Strong move
    Identifies the critical path and builds test points into it.
  5. Candidate
    During the run: evals on checkpoints at agreed points, with go/no-go decisions on criteria set now: what results continue the run, what would stop it.
  6. Interviewer
    Risks?
  7. Candidate
    Hardware failures, so checkpointing often and spare capacity; data issues found late; evals not ready in time. Each in a risk log with an owner, reviewed weekly.

The strong answer, distilled

  • Workstreams: data, compute, training infra, evals, safety, each owned.
  • Critical path: data freeze and cluster reliability.
  • Milestones: data freeze, burn-in, small test run, start, checkpoints.
  • Decisions: go/no-go criteria set in advance.
  • Risks: hardware, data, eval readiness; owned and reviewed weekly.

This is one strong answer, not the only one.

How it's scored

Dimension Weak (2) Passable (3) Strong (5)
Structure Task list Workstreams Workstreams with dependencies
Path None Milestones Critical path with test points
Governance None Risks Decision criteria and owned risks

Round scorecard: AI TPM: execution round, filled in for the mock candidate

DimensionWeakPassableStrongThe mock candidate
Situation assessmentReacts immediately.Gathers some facts.Establishes severity, owners and the critical path before acting.Strong. Mapped workstreams and dependencies.
OptionsOne option.Two options.Several options, each with cost, risk and who decides.Strong. Decision points with criteria.
StakeholdersWorks alone.Informs leaders.Gets the right owners in the room early, with a clear ask.Strong. Owners named per workstream.
Follow-throughStops at the decision.Updates the plan.Updates plan, risk log and communication, and checks the fix.Strong. Risk log and contingency for failures.

How the answer changes by role

Role What to emphasise
AI TPM The programme
Model PMProduct Manager. Decides what a product should do, for whom, and why. Read the full explanation Eval readiness and decision criteria

Common mistakes

  • No small test run
  • Decision criteria made up mid-run
  • Unowned risks

More follow-ups to practise

  • "A data issue is found after start." Hint: stop, fix, or continue? criteria.
  • "Research wants to change the plan mid-run." Hint: change process and cost.

Go deeper

Sources

Representative question: written to match execution rounds for AI product roles, not a specific reported interview.