There Aren't Enough GPUs. Who Gets Them?
The interviewer asksNew GPUs are delayed by two months. Demand from three products exceeds capacity by 30%. How do you allocate?
AI Infrastructure PMAI TPMAdvancedTechnical roundRepresentative10 min
On this page
The 30-second version
- Quantify demand vs capacity by product and time of day.
- Free capacity first: efficiency (quantisation, batching), moving batch work off-peak, routing to smaller models.
- Then prioritise by impact: revenue, commitments, users affected.
- Options with explicit costs: rate limits, waitlists, delayed launches.
- Get a decision from leadership; communicate to affected teams and customers.
What it's really testing
- Capacity crisis management
- Efficiency levers
- Decision-making
How to structure your answer
- Quantify.
- Free capacity.
- Prioritise.
- Options and decision.
The interview, played out
- InterviewerNew GPUsGraphics processing unit. The chips most AI models are trained and served on. Read the full explanation are delayed two months. Demand from three products exceeds capacity by 30%. How do you allocate?
- CandidateFirst, quantify: demand per product, by hour. A 30% gap at peak but not overnight is a different problem from 30% all day.
- Revealed when askedThe gap is mostly at peak hours.
- CandidateThen free capacity before cutting anyone: move batch and internal jobs to off-peak, quantise models where evals allow, route simple requests to smaller models. That might close half the gap.
- Strong moveUses efficiency before rationing.
- CandidateFor the rest, options with explicit costs: delay one product's planned expansion; rate-limit free tiers at peak; waitlist new large customers. I'd bring leadership those options with the revenue and user impact of each.
- InterviewerWho decides?
- CandidateLeadership, with our recommendation. Then tell affected teams and customers early.
The strong answer, distilled
- Quantify: gap mostly at peak.
- Efficiency first: off-peak batch, quantisation, routing; maybe half the gap.
- Options: delay expansion, peak limits on free tiers, waitlist new large customers.
- Decision: leadership with a recommendation; early communication.
This is one strong answer, not the only one.
How it's scored
| Dimension | Weak (2) | Passable (3) | Strong (5) |
|---|---|---|---|
| Analysis | Even split | Total gap | Gap by product and hour |
| Levers | Cut | Prioritise | Efficiency first |
| Decision | Decide alone | Escalate | Options with costs and a recommendation |
Round scorecard: AI Infrastructure PM: technical round, filled in for the mock candidate
| Dimension | Weak | Passable | Strong | The mock candidate |
|---|---|---|---|---|
| Structure | Jumps to a number. | Some steps. | Formula first, steps said out loud. | Strong. Quantified the gap per product. |
| Assumptions | Hidden or wrong. | Stated. | Stated, reasonable, and the sensitive ones identified. | Strong. Stated what each product loses under each option. |
| Technical depth | Weights only. | Weights and throughput. | Weights, KV cache, batching and latency targets. | Strong. Used efficiency levers before cutting. |
| Product judgment | Stops at the number. | Mentions cost. | Turns the estimate into a capacity and cost decision. | Strong. Took options to decision-makers. |
How the answer changes by role
| Role | What to emphasise |
|---|---|
| AI Infrastructure PMProduct Manager. Decides what a product should do, for whom, and why. Read the full explanation | Efficiency levers and capacity |
| AI TPMTechnical Program Manager. Owns plans, dependencies, risks and delivery for large cross-team programmes. Read the full explanation | Running the allocation decision |
Common mistakes
- Splitting evenly
- Rationing before efficiency
- Late communication
More follow-ups to practise
- "A product launch is due in this window." Hint: delay or limit; cost of each.
- "Cloud burst capacity is available at 3x price." Hint: worth it for revenue-critical peaks?
Go deeper
- Module: Inference and serving
- Framework: Back-of-Envelope Method for AI Numbers
- Framework: Explain a Concept Framework
- Framework: Opening Any Interview Answer
- Lesson: Capacity and cost planning
- Lesson: Compute capacity planning
- Also tests: AI programme management
Sources
Representative question: written to match technical rounds for AI product roles, not a specific reported interview.